CS Energy says the Callide C Power Station joint venture (JV) has revised the initial return to service date for Unit C3 by 17 days, with the unit forecast to partially return to service on 24 January 2024 (previously 7 January 2024).
There is no change to the forecast dates for Unit C3โs return to full capacity or the return to service dates for C4.
Related article: Return to service delays for Callide C generating units
CS Energy is rebuilding the two Callide C cooling towers to enable the safe return to service of Callide C Power Station.
CS Energy CEO Darren Busine said the shift in Unit C3โs partial return to service reflected the impact of recent rain and hot weather, resourcing challenges, including illness and COVID-19 at site, and global supply chain issues. This includes some of the assigned freight carriers being diverted to assist with humanitarian efforts in the Gaza War and domestic issues in India which have impacted the scheduling and delivery of materials.
Busine said significant progress has been made on the construction of the new C3 cooling tower, with approximately 165,000 hours worked on site which is equivalent to more than double the standard site workforce.
โWe prioritised the Unit C3 cooling tower as the first of the new cooling towers to be built and there has been an unprecedented level of activity at site to make this happen,” he said.
โApproximately 300 people are working around the clock, seven days a week on site and a logistics specialist has coordinated the movement of more than 1,000 tonnes of freight from all corners of the world.
โIn parallel to the construction activity, CS Energy is working through a commissioning program for Unit C3. This will involve a series of tests, including briefly running the unit at low loads to support its partial return on 24 January.
Related article: CS Energy completes bulk of rebuild on Unit C4 at Callide
โThis is a highly complex and unique project, and I would like to acknowledge the efforts of eveyone involved to progress the works to this stage.
โOur first priority is the safety of our people and plant. I would like to reassure Queenslanders that we are doing everything we can to have the unit back online as soon as possible.โ